Herbrand Street Estate Works

This topic contains 4 replies, has 3 voices, and was last updated by  Paul Ginsberg 2 months, 1 week ago.

Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • #4261

    Jez
    Participant

    Just been informed that the work on the 3 blocks in Herbrand Street will continue until the end of August!

    Initially new windows, roof and brickwork was planned from November 2016 – March 2017. This slipped to April 21 2017. Chased again as not many people on site and now its going to go on until the end of August 2017!

    Not only are leaseholders being burdened with a huge bill for these works, the incompetence of the planning to complete these works is amazing!

    #4269

    Peter Wright
    Participant

    Jez,

    I am not aware of any resident activity in Herbrand Street. Do you have meeting with Camden or some form of tenants and residents association?

    Peter Wright

    #4274

    Jez
    Participant

    Hi Peter, sorry did not spot this reply.

    Not aware of any tenant / leaseholder association for the estate. And as for contact with Camden, reams and reams of documents about tenders etc but only one letter confirming the start of the work. I have had to ask Camden each time for an update on each time the completion date passes. Estimated invoices total £19k for this work!!!!

    #4275

    Peter Wright
    Participant

    Thanks. If they have never offered any form of meeting, I am happy to ask Tenant Participation to contact you and set one up. If that suits, how should you be contacted?

    Peter Wright

    #4276

    Paul Ginsberg
    Participant

    Hi Folks. Rather than exchange details in public, I’ll give you each other’s email addresses (or you can also use the messaging facility on this discussion board).

    Best regards,
    Paul
    Discussion Board Maintainer 🙂

Viewing 5 posts - 1 through 5 (of 5 total)

You must be logged in to reply to this topic.