Herbrand Street Estate Works

Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • #4261
    Jez
    Participant

      Just been informed that the work on the 3 blocks in Herbrand Street will continue until the end of August!

      Initially new windows, roof and brickwork was planned from November 2016 – March 2017. This slipped to April 21 2017. Chased again as not many people on site and now its going to go on until the end of August 2017!

      Not only are leaseholders being burdened with a huge bill for these works, the incompetence of the planning to complete these works is amazing!

      #4269
      Peter Wright
      Participant

        Jez,

        I am not aware of any resident activity in Herbrand Street. Do you have meeting with Camden or some form of tenants and residents association?

        Peter Wright

        #4274
        Jez
        Participant

          Hi Peter, sorry did not spot this reply.

          Not aware of any tenant / leaseholder association for the estate. And as for contact with Camden, reams and reams of documents about tenders etc but only one letter confirming the start of the work. I have had to ask Camden each time for an update on each time the completion date passes. Estimated invoices total £19k for this work!!!!

          #4275
          Peter Wright
          Participant

            Thanks. If they have never offered any form of meeting, I am happy to ask Tenant Participation to contact you and set one up. If that suits, how should you be contacted?

            Peter Wright

            #4276

            Hi Folks. Rather than exchange details in public, I’ll give you each other’s email addresses (or you can also use the messaging facility on this discussion board).

            Best regards,
            Paul
            Discussion Board Maintainer 🙂