      Hi emmersch, I’d be happy to send you a video of how the pipework has been done in our flat, and alongside that I could send you the drawing (to which there was one fairly major change in execution, which I can outline). I can’t see how Camden have not committed to make good? In carrying out the work, they have to knock through walls etc to run pipework, so have to fill all that back in. For us, they could make good but only with white paint, though said if the resident still had specific paint that matches a room, the workmen should be fine to use that instead.

      in reply to: Maiden Lane heating major works – working together #7371
      imogenisabelle
      Participant

        We had the same heating works already done on the St Silas Estate (and others have been done before and since; I think they’re in Denton now). When they visit you, they will produce drawings of the work/piping, and there is some latitude to find better solutions.

        The works have to be done because of new(ish) Heat Network (Metering and Billing) Regulations https://assets.publishing.service.gov.uk/media/5fce3739e90e07562aba0de7/heat-networks-guidance-on-metering-and-billing-regulations-2014.pdf

        It’s not possible for them to go into the floors, nor use the existing pipework, as the problem is the pipework has all the flats linked together, which is exactly what they’re undoing. The external pipework is generally not as obstructive or ugly as I was worried about, though it’s not ideal and there are certain places I dislike it. Most of the piping is not boxed in, but painted white, and most of it runs at skirting level, and on relatively few walls, depending on the layout and number of radiators in your home.

        The make good was quite poorly done in our home – our walls are all white, so that was easy, but I went into labour during the heating works (yes, really) and my sister-in-law had to oversee the works for us while I was in hospital, and when I came back they obviously wanted to clear out as quickly as possible as I had a newborn. It’s something I’m sure we could have been more dogged about getting people back to fix the last few things, but generally speaking they’re things we can fix with a bit of DIY.

        I really empathise, it’s a huge pain and hugely disruptive at the time, but the result is less bad than I feared.

        in reply to: Major Works-WhatsApp Group #6478
        imogenisabelle
        Participant

          Thousands of pounds adjustment down, rather than up? If so, very likely it will be because they haven’t been able to carry out the works in that period and so can’t charge in that period for works not done in that period.

          in reply to: Gaisford Street – Major works charges #5796
          imogenisabelle
          Participant

            Hi Liv, could you post again if you get anywhere with ascertaining how the costs under ‘Property Details’ fit into all of this? Or send me a message. Thank you.

            in reply to: Gaisford Street – Major works charges #5764
            imogenisabelle
            Participant

              Hi Jay,
              Pretty sure that won’t be possible. Apart from not knowing whether or how it would be physically possible without using the same communal boiler (they are having to dig up the street for new underground piping and providing new piping to each flat – you would presumably still need to use that piping so you would be part of that work – we’re not just paying for interior work).
              But crucially, as the freeholder, supply of heating and hot water comes under their obligations in the lease – and that will create huge problems for the next leaseholder of your flat, and for Camden then.

              in reply to: Gaisford Street – Major works charges #5755
              imogenisabelle
              Participant

                I am in a similar situation to Jerome (St Silas Estate heating works) and feeling completely overwhelmed in the face of such an enormous bill, but also so powerless. Trying to communicate with Camden is nigh on impossible and even if I request a further itemised breakdown of the estimated costs, what will I then do with that information? Christopher, I will send you an email now.